The Row Residence: Progress On-Site

Work is well underway at The Row Residence, and it is rewarding to see this family home take shape.
 
Our team is now fully immersed in the delivery stage, working closely with our specialist consultants and contractors to ensure the architectural and interior vision is executed with absolute precision.

Construction is progressing at pace, with several key milestones now achieved:
 

  • Structural Progress:
    Piling is 100% complete, and the rear retaining wall is now 100% finished.
     

  • Basement & Foundations:
    Basement excavation is currently underway, alongside the foundation details for the new Garden Room.
     

  • Heritage & Craft:
    We have successfully completed the façade retention, and works are now focused on the ground-level detailing of the existing façade, where we are carefully incorporating salvaged bricks to honour the home’s original character.

  • Seeing our designs move from the drawing board to the reality of the construction site remains one of the most rewarding aspects of our process.
     
    We look forward to sharing further updates as the project progresses!